Zabrđe Transformer Substation

Zabrđe Transformer Substation

The substation was completed in October 2025.

Project: Construction of the Zabrđe metal-clad transformer substation (2 × 1,000 kVA, 10 kV)

Purpose: Connection of solar power plants to the grid

MV and LV equipment: Loznicaelektro doo, Loznica, Serbia

Transformers: 2 × 1,000 kVA, 10/0.4 kV

Manufacturer: Transformer Energy, whose equipment we import and distribute

Project information

Zabrđe Transformer Substation
Ugljevik
2 × 1,000 kVA, 10 kV
Cart