Zabrđe Transformer Substation
The substation was completed in October 2025.
Project: Construction of the Zabrđe metal-clad transformer substation (2 × 1,000 kVA, 10 kV)
Purpose: Connection of solar power plants to the grid
MV and LV equipment: Loznicaelektro doo, Loznica, Serbia
Transformers: 2 × 1,000 kVA, 10/0.4 kV
Manufacturer: Transformer Energy, whose equipment we import and distribute
Project information
Zabrđe Transformer Substation
Ugljevik
2 × 1,000 kVA, 10 kV